How long did it take to fully decommission your legacy data systems after your cloud migration? How do you estimate the required timeline?

5.9k viewscircle icon2 Comments
Sort by:
Director of IT in IT Servicesa year ago

It’s all depends on how large the environment and what’s in the scope for decommission. For a 100 racks environment, including scraping the disks, recycling the cabling to decommissioning the HVAC and DC floor takes around 2 months.

CIO2 years ago

The timeline for decommissioning legacy data systems post-cloud migration can vary based on factors like the complexity of the architecture, data volume, and specific business requirements. In my experience, the process typically takes several months to a year. Estimating the timeline involves a detailed assessment of the existing systems, mapping dependencies, and creating a phased plan for data migration and decommissioning. Thorough planning, testing, and a well-defined transition strategy will surely contribute to a smoother and more efficient decommissioning process.

Content you might like

Virtualization Strategy and Implementation20%

Hyper-Converged Infrastructure (HCI) Adoption55%

Infrastructure Observability and Monitoring35%

Cloud-Based Backup and Shared Infrastructure Services from local vendors30%

Software-Defined Infrastructure and Automation30%

Edge Computing and Edge AI Implementation10%

Advanced Data Center Cooling Technologies5%

Hardening of existing Infrastructure10%

View Results

Talent30%

New technology67%

Existing technology45%

Process management20%

Something else

View Results